The completed hand-painted Paddock Club facade at Yas Marina Circuit

Case study · Monumental mural delivery

Yas Marina
Circuit

Paddock Club & Team Villas
Abu Dhabi, UAE

Two annual commissions
Q4 2024 + Q4 2025

↓︎

The commission

One master project.
Two exacting deliveries.

Gallery Dod delivered two separate annual commissions within the same master project across the Paddock Club and Team Villas at Yas Marina Circuit.

The responsibility extended beyond execution: feasibility study, design planning, designer acquisition, full design IP purchase and transfer, project scheduling, safety planning, equipment hire, safety training and hand-painted mural delivery.

Client
Ethara
Delivery partner
XLer8 AD
4,000–5,000approximate square metres per annual commission
02annual commissions within one master project
Hand paintedacross façades, corridors and architectural elevations
Live sitedelivered alongside Grand Prix advance operations

Commission 01 · Q4 2024

The first delivery.
A defining gesture.

Gallery Dod undertook the same complete remit, from feasibility, design planning and full design IP purchase and transfer through scheduling, safety, equipment, training and mural execution. The monumental staircase became a focal point within the wider Paddock Club and Team Villas commission.

Completed Paddock Club exterior at Yas Marina Circuit with the monumental mural integrated into the architecture
01 Paddock Club · completed architectural context
Completed monumental calligraphic mural above the Yas Marina Circuit staircase
02 Commission 01 · completed architectural mural
The completed monumental mural rising through the Paddock Club staircase
03 Paddock Club staircase · finished interior perspective

Built around the site

Complex access.
Controlled execution.

The execution demanded a level of control appropriate to a live, high-profile venue. Full-height access, night shifts and exacting coordination allowed the design to hold together across every level and viewpoint.

Gallery Dod mural crew working across aligned full-height scaffolding at Yas Marina Circuit
04 Full-height access · controlled execution
Specialist mural crew working at night across the Paddock Club elevation
05 Night operations · specialist crew
Artists working across multiple levels of the Paddock Club at night
06 Paddock Club · multiple working levels
Gallery Dod team working across a multicoloured Paddock Club elevation at night
07 Commission 01 · precision at architectural scale

Commission 02 · Q4 2025

The brief returned.
The standard held.

Gallery Dod returned for a second separate commission within the same master project, carrying the same end-to-end responsibility into another demanding race-week delivery.

Completed mural spanning the illuminated Paddock Club
08 Paddock Club · completed elevation
A completed row of hand-painted Team Villas at night
09 Team Villas · repeated architectural scale

The operational challenge

A working environment
that never stood still.

The commission progressed while Formula 1 advance teams, hospitality contractors, technical crews and venue operations prepared the circuit for the final race. Gallery Dod’s schedule had to remain precise while access, movement and priorities changed around it.

Every elevation required a workable sequence, with crews, equipment, safety controls and painting windows coordinated without losing the integrity of the overall design.

The Team Villas and Yas Marina Circuit under Grand Prix preparation at night
10 Circuit context · Grand Prix preparation
Access in motionBoom lift deployment · Team Villas

Work at height

Access was part
of the design.

Scaffolds, scissor lifts and boom lifts were selected and scheduled by zone. Equipment movement, safety inductions and working positions were resolved as part of the production plan, not treated as an afterthought.

Elevated view of the Team Villas with lift equipment operating below
11 Multiple work fronts · night operations
Multiple scissor lifts positioned along the Team Villas
12 Parallel delivery across repeated façades
Artists painting the Team Villas from elevated platforms
13 High-access mural execution

Paddock Club

One visual language.
Many architectural conditions.

The design had to retain rhythm and continuity across long elevations, doors, cameras, lighting, glazing and changing working distances. Translation happened directly against the building, measured, adjusted and resolved by hand.

Artists working from scaffold across two Paddock Club levels
14 Design continuity across levels
Artist painting from a scaffold at dusk
15 Paddock Club · dusk shift

Direction & control

Every shift began
with alignment.

A founder-led delivery model kept creative, technical and operational decisions connected. Briefings, daily access checks and live design review gave each specialist crew a clear scope while allowing the programme to respond to the site.

Gallery Dod team receiving an on-site briefing
16 Crew briefing · Paddock Club
Project planning and coordination taking place on site
17 Live planning and design review

Executed by hand

Large scale.
Human precision.

At distance, the work reads as one continuous architectural gesture. Up close, it is the accumulation of thousands of controlled decisions: line, edge, proportion, colour and the consistency of one hand-painted surface after another.

Artist hand painting the mural from a lift
18 Brushwork at elevation
Artist rolling paint onto a large Team Villa mural
19 Scale translated by hand
Gallery Dod branded safety helmet beside precise mural brushwork
20 Gallery Dod · on site

The completed environment

Built into the architecture.
Ready for race week.

Completed Team Villa mural beside Formula 1 team signage
21 Completed Team Villa · F1 team branding in place
Completed mural along the Paddock Club corridor
22 Paddock Club · handover condition

Delivery

A team assembled
around the work.

Gallery Dod led the commission and brought together the artists and specialist crew required by the site. XLer8 AD supported delivery as project partner.

Gallery Dod and XLer8 AD reviewing a Team Villa elevation on site
23 Site review · Gallery Dod + XLer8 AD
The Yas Marina Circuit project delivery team
24 Project delivery team · Q4 2025

Have a difficult site?

Bring us the
unusual brief.

Start a project ↗︎